steel design

ISSUE No. Two VOLUME 50

Autumn 2018

Prefabricated Light Steel Framing and Prefab Panels save time

The reality behind Interbuild Limited’s pre-fabricated lightweight cold formed steel wall, structural floor and roof framing systems is simplicity and efficiency.

Interbuild’s pre-fabricated steel wall panels, together with a faster construction time make these materials a no-brainer – a cost-effective alternative to traditional building. That is why Habitat For Humanity used this method for a recent project in Hamilton.

Cold formed steel provided lower construction costs, reduced insurance costs, plus the added benefit of non-combustibility.

“The trigger for the project was the Habitat for Humanity Canadian Conference coming to Hamilton,” said Tom Vert, Vice-President of Manufacturing for ArcelorMittal Dofasco. “We were trying to figure out what we could do differently for that conference and we brainstormed saying, it’s Steeltown, why don’t we build a steel house during the conference?”

Vert added that, for the project, he did some research on companies that do steel prefab housing. “In Ontario there are approximately three companies that do it,” he said. “We went and did some research and found that Interbuild was the best fit for us. They had the product, they had the ability to do it and Ivano was kind enough to donate his time and expertise to do the design work as well as to the fabrication and installation.”

The Ivano that Vert is referring to is Ivano Minatel, the owner of Interbuild Limited, a company which specializes in prefab Cold Formed Steel applications.

“We have both an engineering-based firm here and an installation company,” said Minatel. “On the engineering side, from an architectural drawing, we will design the LSF walls and roof systems, if that should be the case, as well as some of the floor systems.”

Minatel then outlined the rest of the process, saying that everything is integrated together in Revit format so there is an actual model to work from. Interbuild then manufactures all the walls and ships everything out to the build site and they install it.

The frame of the building was constructed by Interbuild using state-of-the-art 3D modeling software to design and frame all the cold formed steel load bearing and non-load bearing walls.The prefabricated wall panels are assembled off site. The panels are then shipped to the site and installed, negating the need for space to build and store the materials on site. The floor system in this case for a single dwelling is CFS joists pre-panelized floor with plywood sheathing.

The framing and prefabricated panels for the building were constructed by Interbuild Limited using state-of-the-art, efficient on-site panel erection assembly system, where the walls are framed off-site as panels.

After construction of the structural frame was completed, traditional interior steel stud partition walls were installed to complete the interior framing.

The process is “at least as good as traditional construction and in certain applications, style and types of building, it is a much better application,” he said. Regarding the Habitat for Humanity Hamilton project, the construction portion was done in 3 days for a two-floor structure.

Humanity Hamilton project, the construction portion was done in 3 days for a two-floor structure.

The panels are then shipped to the site and installed, negating the need for space to build and store the materials on-site. As well, this allows services such as electrical wiring and plumbing to be expediently installed, providing time and cost benefits to your project.

“It is a concrete slab with two floors and a roof,” said Vert, who also has a lot of praise for the process. “If you try doing steel studs by stick-and-frame, it takes a long time. By doing it prefab in a warehouse, you just drop all the sections right in place. The first floor was done in just three hours.”

Vert pointed out that “speed of installation and construction” are the main benefits. “You know that when you build it in a factory, you’re not affected by any kind of weather.”

By using prefabricated wall panels, pre-assembled roof trusses and selected floor systems, Interbuild can complete your project in a fraction of the time that it would take with wood/concrete frames.

Wall Panel, Floor and Roof layout drawings are used for coordination by the on site erection team. This process ensures that the shell structure is built accurately and on schedule.

In-house Engineers provide structural designs according to the International Building Code, United States Building Code, the National Building Code of Canada and Building Codes for the Caribbean.

Engineered CFS wall panels are prefabricated with exceptional precision in a controlled environment, versus unpredictable field conditions. This not only guarantees a higher degree of quality, but it also prevents unexpected schedule delays due to weather conditions and other factors.

Using engineered prefabricated CFS wall panels, pre-assembled roof trusses and selected floor systems Interbuild can complete your project in a fraction of the time needed for wood/concrete frames, resulting in faster on-site erection, minimal on-site wastage as well as savings in on-site storage space of raw materials.

The increased use of new techniques using steel helps reduce costs of the overall project and makes projects like this more marketable since steel is inherently a stable, engineered material with consistent properties and attributes.

Interior view showing prefabricated roof trusses, exterior pre-assembled wall panels and interior wall studs. The floor system is comprised of a CFS panel system with a reinforced concrete overlay.

Finishing off the exterior is Stratus vertical wall cladding and AR38 Panels on the roof.
Due to the deadline date for publishing Steel Design we will show the finished project in the Spring 2019 issue.

Interior view of buildings steel beams
COLD FORMED STEEL FRAMING SECTIONS:

• 600S162-43 Structural steel stud: 6” web, 1 5/8” flange, .043” thick

• 600S200-33 Structural steel stud: 6” web, 2” flange, .033 thick

• 600T125-43 6” web, 1.25” flange, .043” thick

• 362T125-54 3 5/8” web, 1.25” flange, .054” thick

• 362T125-68 3 5/8” web, 1.25” flange, .068” thick

• 362S162-68 Structural steel stud: 3 5/8” web, 1 5/8” flange, .068” thick

• 800S200-54 Structural steel stud: 8” web, 2” flange, .054” thick

• 1200T125-97 12” web, 1.25” flange, .097” thick

• 1200S200-97 Structural steel stud: 12” web, 2” flange, .097” thick

ROOF CLADDING:

• AR38Panels:.61mm(.0239”)pre-painted galvanized, coloured Graphite Grey QC 60035 in the Deep Mat paint system.

WALL CLADDING:

• Stratus vertical cladding hidden fastener panels: .45mm (.0179”) pre-painted galvanized, coloured QC28730 Regent Grey in the Perspectra Series paint system.

ROOF DECK:

• .76mm (. 0299”) pre-painted galvanized RD36 cladding Lap panels.

DESIGN AND CONSTRUCTION TEAM OWNER:

Habitat for Humanity

PREFABRICATED COLD FORMED STEEL WALL PANELS STRUCTURAL FLOOR AND ROOF SYSTEM:

Interbuild Limited Prefab Systems 905-482-1919

ROOF AND WALL CLADDING SUPPLIER:

Agway Metals Inc. 1-800-268-2083

ROOF AND WALL CLADDING INSTALLER:

John Kenyon Ltd. 905-527-2721

COLD FORMED STEEL SUPPLIER:

Bailey Metals Products 1-800-668-2154

STEEL ROOF DECK SUPPLIER:

Agway Metals Inc. 1-800-268-2083

PHOTOGRAPHER:

JOE BUCCI 905-730-1985

Explore this issue:

Behlen’s Design and Manufacturing Expertise –three Indoor Arenas in Georgia

Steel is so incredible for construction projects that it is known the world over for its versatility and durability. That is why, when it came time to build three indoor arenas in the Republic of Georgia, Behlen Industries was tapped to construct these steel-based structures for all to enjoy. “Two of them are the same size and the third is a little bit bigger,” said Dave Fletcher, Director of International Sales for Behlen in an interview with Steel Design.

Fletcher went on to add that it was a long process to get the deal done in Georgia in order to build these structures but, by partnering with the right people the project became a reality. “One of the arenas is in Plavi the other one is in Gori, which is (interestingly) where Joseph Stalin […]

READ MORE

Gary W. Harris Canada Games Centre, Red Deer College

When the City of Red Deer approached Red Deer College about hosting the 2019 Canada Winter Games, it was a catalyst for finally realizing a dream. The college had been planning a new facility focused on health education, sport and recreation for years. The new Gary W. Harris Canada Games Centre will host five Canada Winter Games events, including Short Track Speed Skating, Figure Skating, Badminton, Wheel Chair Basketball and Squash.

“We envisioned a facility that would be learner-centred; support teaching, learning and the student experience; provide for sport and lifestyle fitness and be available for community use,” says Doug Sharp, the college’s Director of Capital Projects. “The facility would contribute to the economic, social and inclusive wellbeing of the central Alberta region and would become […]

READ MORE

Galvalume Plus™ accentuates the new tent-like roof

The unpainted 30,000 shingles in “À la Canadienne” shingle pattern, manufactured from .45mm and .61mm (.0179” and .0239”) Galvalume Plus™ help the tent-shaped roof of the church, now functioning as a public library, brilliantly reflect snow and sky and reach to the heavens. The shingles blur the distinction between snow, roof and sky, and complement the glass-walled extensions to the building.

The architects teamed-up to complete the Monique-Corriveau Library, which involved an addition to and conversion of the St-Denys-du-Plateau church in Québec City. Built in 1964, the church is a landmark example of modernism in the region, featuring a tent-like form and it served parishioners until it was closed in 2009. In the fall of 2013, […]

READ MORE

Corrugated AZM150 Galvalume® steel cladding – fit for a Harley!

With a steel exterior and towering presence, the unique Premont Harley-Davidson dealership on the outskirts of Quebec City, like the motorcycles themselves, is built to be admired. Opened for business in August 2012, the approximately 8,000m2 (86,000 sq. ft.) building contains a showroom, boutique, repair shop, museum and even a restaurant.

Located at 1071 Boulevard Pierre-Bertrand, near the axis of Route 358 and Autoroute Félix-Leclerc (A40), the building is sheathed with 2,787m2 (30,000 sq. ft.) of 0.61mm (.0239”) 22.2mm (7/8”) cor- rugated AZM150 Galvalume steel cladding, coloured QC2642 Silver. Why Galvalume? “It was a question of economy. The choice of a metallic exterior facing is economical. […]

READ MORE

LustreLok™ – the Advanced Acrylic Coating for Galvanized Steel

LustreLok™ is a thin, clear organic coating, applied to both sides of the galvanized steel as a final protective layer over the zinc coating. LustreLok provides an attractive appearance and enhances the traditional look of galvanized steel. The application of an organic coating eliminates the need for ArcelorMittal to apply conventional chemical treatment and vanishing oil.

This enhancement offers our customers and users the following benefits: REDUCED COSTS: • The product is designed to be roll formed dry, which eliminates the need for lubricants • Lower maintenance costs – reduced coating build-up and reduced tool wear will extend die life. • Improved productivity – extended die life results in longer production […]

READ MORE