Steel Design

ISSUE No. One VOLUME 50

Spring 2018

Pre-painted Galvanized Steel Cladding contributes to re-cladding project

The Victoria Park Transfer Station is a waste drop-off and transfer facility located in North York, Ontario. It is owned by the City of Toronto. Completed in 2017, the re-cladding project rehabilitated nearly the entirety of the building’s exterior. Cole Engineering was the prime consultant working with ATA Architects Inc. as the sub-consultant, responsible for the architectural components.

The waste transfer station was built in the 1970s by Inducon Consultants of Canada Limited. The original brick building was constructed without a rain screen cavity. As a result, moisture entering the masonry wall due to rain and/or the migration of moisture in the form of vapour from within, was unable to drain away effectively. When the brick froze in the winter, any pre-existing moisture was unable to escape.

The brick consequently fractured and its outer face spawled off. The masonry damage that had occurred over the years was significant and extensive. To remediate local damage a portion of the building had been previously re-clad in a dark brown siding.
Conservation architects ATA were brought onboard to review and remediate the damage. Simply repairing and replacing the damaged masonry would not have prevented further deterioration as the root cause of the problem (trapped moisture) would not have been remedied. ATA frequently work to retain original materials, but in this instance, it would have been counterproductive.

Instead, ATA re-clad the building in pre-painted steel siding. The building has minimal windows and a substantial area of wall surface to cover. ATA’s chosen approach was to use standard industrial-type siding in various profiles and colours to provide contrast and give character to the building.

East Elevation

East Elevation

Wall Section

ATA believed that an extension of the existing dark siding over the building’s remaining elevations would make for an oppressive and foreboding appearance. The original design had located windows and vents in vertical strips to break down the massing and provide more visual interest.

In the same spirit, ATA retained these elements and used them to break the patterning of the steel siding. To create continuity between the existing and new siding, ATA also incorporated dark brown panels.

The brick was removed to the concrete block wall. Added: Blueskin self-adhered air and vapor barrier membrane, rigid insulation, then fastened Z bars (metal skirt system), then installed steel siding (in horizontal or vertical orientation, depending on the section of the wall). Structural steel was added to the back of block walls more than 9.14m (30 ft.) in height, because the brick was bonded to the block and part of the structure.

Victoria Park

Typical Wall Section: Brick was removed, Blueskin self-adhered air and vapor barrier membrane and rigid
insulation were added. Once Z bars were installed, both vertical and horizontal siding was installed,
depending on the location.

Victoria Park View

ATA’s chosen approach was to use standard, industrial-type siding in various profiles and colours to provide contrast and give character to the building.

A brick screen wall approximately 144.8m (475 ft.) in length and up to 5.73m (18.8 ft.) high separates the station from its immediate neighbour, a commercial plaza to the west. The wall, like the transfer facility itself, had deteriorated significantly over time. It too was constructed at a time when rain screen principles were not commonly applied to masonry. As such, the scope of the architectural work also included its re-construction.

ATA’s approach and choice of material resulted in a lower client investment cost with a double win: extending the life of the building and, improving the aesthetics of the building and the streetscape for the users and the neighbourhood.

The original brick building and screen wall, was constructed in the early ‘70s without a rain screen cavity, which was common at that time. As a result, the moisture entering the masonry wall was unable to escape. This then resulted in fracturing and the outer surface of the brick spawling falling off. With the root cause of the problem being trapped moisture, simply repairing and replacing the damaged masonry would not have prevented further deterioration.

DESIGN AND CONSTRUCTION TEAM OWNER:

City of Toronto

ARCHITECT:

ATA Architects Inc. 905-849-9686

STRUCTURAL ENGINEERS:

Cole Engineering 905-940-6161

GENERAL CONTRACTOR:

Duron Ontario Ltd. 905-670-1998

WALL CLADDING SUPPLIER:

Vicwest 800-387-7135

WALL CLADDING INSTALLER:

Cladit Siding Solutions Inc. 416-738-9671

PHOTOGRAPHER:

Victor Lee

STEEL WALL CLADDING

Pre-painted Z275 (G90) galvanized, with a silicone modified polyester paint system

• Vicwest AD 300R Siding Colour: QC-16082 Regent Grey

• Vicwest CL6025R Siding Colour: QC-16072 Charcoal)

• Vicwest Corrugated Siding Colour: QC-16071 Stone Grey

BRICK

• Brampton Brick Premier Plus size, Red Smooth

Explore this issue:

UltraBond Floor System speeds up Apartment Building Construction

A composite floor system shortened construction time by three months and cut material costs, for an 11-storey, 166-condo unit apartment building in Longueuil Quebec. The system, called UltraBond, comes in cold-form sheets 609.6mm (24 inches) wide, 203mm (8”) high and precut in lengths up to 10.06m (33 ft.), according to Simon Pawsey, technical sales representative with the Steelform Group of Companies.

Once assembled into floor decking and with rebar placed in the deep V-grooves, concrete is poured on the Ultra-Bond, creating a lightweight composite floor 292mm (11.5”) thick. Once finished, it has a two-hour fire rating. Pawsey checks off some of the advantages of this construction technique: “UltraBond significantly reduced weight on the structure compared to […]

READ MORE

Steel and the sound of music

The Taylor Performing Arts Centre is music to students’ ears at Mount Royal University in Calgary. Designed by Pfeiffer Architecture, construction on the new addition to the school was begun in 2011 and finished in the Fall of 2015. The Centre’s crowning glory is the 800-seat Bella Concert Hall, which features a stunning Alberta rose […]

READ MORE

Pre-Painted Steel Cladding Integral to the North

The new Aquatic Centre in Iqaluit, Nunavut, has revitalized the community and helped to teach another generation of residents how to swim. Joshua Armstrong, architect and Iqaluit office manager for Stantec Architecture in Iqaluit, had his work cut out for him when he was hired to spearhead the project in 2013. The Iqaluit Aquatic Centre was completed in December 2016.

“It’s an aquatic centre first with community centre elements and a fitness facility. It’s Phase 1 of a long-term plan to increase recreational facilities in the community,” he explains. “Since it opened, the response has been overwhelmingly positive. The Centre gets a lot of use.” Stantec’s client for the job, the City of Iqaluit, had […]

READ MORE

Steel Wall Cladding – Versatility, Flexibility and Lightweight

The award-winning Commonwealth Community Recreation Centre (CCRC) is now five years old. Commissioned under the City of Edmonton’s revamped RFP process, the choice of steel for the superstructure and cladding was key in delivering the design excellence and project efficiency called for by Edmonton’s civic revitalization mandate.

The LEED Silver building resulted from a joint-use partnership between the City of Edmonton and the Edmonton Eskimos Football Club. MJMA of Toronto along with local partners HIP Architects (now Kasian) built on and expanded the formerly underutilized site of the 1978 Commonwealth Stadium, cleverly combining: stadium activities, football operations, and a fitness and community […]

READ MORE

Real Steel Cost Advantages – Consider. Choose. Challenge.

Start at the foundation where the loads imposed by a steel frame are up to 50% less than those of a concrete alternative. There is evidence in the field and through third-party case studies and comparative cost studies that steel building systems offer significant cost benefits over competitive building materials when the total cost of construction is considered.

There is evidence in the field and through third-party case studies and comparative cost studies that steel building systems offer significant cost benefits over competitive building materials when the total cost of construction is considered. Building owners, developers, contractors and design professionals are concerned with overall system construction costs from the design phase through the […]

READ MORE